Land At Former Power Station Site On Northern Side Of Cambois Northumberland
Description
Variations of conditions 4 (Approved Plans), 17 (Access), and 51 (Deliveries) of approved application 24/04112/OUTES in order to increase the speed of delivery of the development to meet the requirements of potential tenants of the data centres on site
Nearby new applications
Land At Former Power Station Site On Northern Side Of Cambois Northumberland
Reserved matters application for landscaping and layout on approved application ...
Land At Former Power Station Site On Northern Side Of Cambois Cambois Northumberland
Discharge of Conditions 14 (Construction Method Statement), 34 (Disposal of Surf...
Land At Former Power Station Site On Northern Side Of Cambois Northumberland
Discharge of Condition 13 (Phasing Plan) pursuant to planning permission 24/0411...
Land At Former Power Station Site On Northern Side Of Cambois Cambois Northumberland
Reserved matters application for (Landscaping and Layout) on approved planning a...
Land At Former Power Station Site On Northern Side Of Cambois Cambois Northumberland
Variation of Conditions 4 (Approved Plans), 17 (Access) and 51 (Deliveries) of a...
Land At Former Power Station Site On Northern Side Of Cambois Cambois Northumberland
Discharge of Condition 7 (Modular Building) of approved application 25/01725/REM
Historical activity at this location
5 nearby applications on record - archival context, not part of the live application.
Nearby activity
North Tyneside is faster than most councils at deciding householder applications, ranking #30 out of 292. Only 23% of applications have the time limit extended, well below the 40% national average - the council usually decides on time. Householder applications are slightly more likely to be approved here (96%) than the national average (90%).